14-023 |
LKR |
$128,314.00 |
$128,314.00 |
$2,309,648.00 |
$0.00 |
$2,566,276.00 |
Install wildlife fencing and place an asphalt surface coarse on the parallel taxiway and connecting taxiways. Rehabilitate taxiway lighting system. |
14-022 |
OGB |
$20,901.00 |
$20,901.00 |
$376,218.00 |
$0.00 |
$418,020.00 |
Install wildlife fence |
14-021 |
CDN |
$30,500.00 |
$30,500.00 |
$549,000.00 |
$0.00 |
$610,000.00 |
Land acquisition for RWY 6/24 safety areas, engineering design for runway safety area, road relocation and highway intersection improvements, and obstruction clearing |
14-020 |
35A |
$9,248.00 |
$9,248.00 |
$166,455.00 |
$0.00 |
$184,951.00 |
Acquire property to the approach of RWY 23 - 1.5 acres of easement from Southside Fire District; Fee simple acquisition of .9 acres from the Palmer estate. |
14-019A |
SMS |
$1,320.00 |
$1,320.00 |
$23,760.00 |
$0.00 |
$26,400.00 |
Amend grant 14-019 to cover change orders associated with apron rehabilitation |
14-019 |
SMS |
$77,357.00 |
$77,357.00 |
$1,392,425.00 |
$0.00 |
$1,547,139.00 |
Rehabilitate terminal apron with a 10" concrete overlay |
14-018 |
CEU |
$22,511.00 |
$22,511.00 |
$405,205.00 |
$0.00 |
$450,227.00 |
Land acquisition to approach end of RWY 7 (4 Parcels, 2.5 acres); engineering design services for a stub TWY; and relocation of a power line. |
14-017 |
CRE |
$160,303.00 |
$160,303.00 |
$2,885,445.00 |
$0.00 |
$3,206,051.00 |
Phase II - Rehabilitate terminal apron with a concrete overlay including construction and construction administration. |
14-016 |
CUB |
$139,006.00 |
$139,006.00 |
$2,502,108.00 |
$0.00 |
$2,780,120.00 |
Phase I - TWY "A" extension (1000') - Environmental mitigation and construction |
14-015 |
GGE |
$22,136.00 |
$22,136.00 |
$398,454.00 |
$0.00 |
$442,726.00 |
Construct T-hangar taxilanes |
14-014 |
UDG |
$27,354.00 |
$27,354.00 |
$492,375.00 |
$0.00 |
$547,083.00 |
Asphalt rehabilitation of the apron and taxilane |
14-013 |
MKS |
$33,269.00 |
$33,269.00 |
$598,840.00 |
$0.00 |
$665,378.00 |
Clear obstructions in the approach to RWY 23 (37 parcels) |
14-012 |
AIK |
$9,740.00 |
$9,740.00 |
$175,325.00 |
$0.00 |
$194,805.00 |
Engineering & permitting services for expanded the terminal apron |
14-010 |
GYH |
$7,080.00 |
$7,081.00 |
$127,448.00 |
$0.00 |
$141,609.00 |
Runway Safety Area and Drainage Improvements for RWY 5-23. Project includes the full design for the airfield and construction of Phase 1. |
14-009 |
GRD |
$157,470.00 |
$157,470.00 |
$2,834,461.00 |
$0.00 |
$3,149,401.00 |
ALP Update; Bidding, Construction, Construction Phase Services, and Grant Services for the pavement and lighting rehabilitation for Runway 9-27. |
14-007 |
EOE |
$56,242.00 |
$56,242.00 |
$1,012,345.00 |
$0.00 |
$1,124,829.00 |
Apron Rehabilitation and Expansion (Construction)
Project consists of rehabilitation of the existing terminal apron and connectors from the apron to Taxiway 'A' and the expansion of the terminal apron. |
14-006 |
3J1 |
$432,694.00 |
$114,923.00 |
$162,000.00 |
$0.00 |
$709,617.00 |
Acquisition of 8 fee simple parcels and 59 easements. Project covers the professional services for closing on the fee simple parcels, professional services for purchasing the easements, and the estimated costs of the easements. |
14-005 |
UZA |
$103,301.00 |
$103,302.00 |
$1,859,426.00 |
$0.00 |
$2,066,029.00 |
Apron Rehabilitation (Construction) including construction administration, inspection and testing. This project includes the design of taxiway filet widening, and the repackaging of the taxiway rehabilitation design. |
14-004 |
MAO |
$57,720.00 |
$38,480.00 |
$0.00 |
$0.00 |
$96,200.00 |
Marion County Airport Terminal Renovation including:
New Rubber Roof, Re-glazing of windows, Window Tinting, Drop Ceiling, Paint, Carpet, VCT Tile, Outside Trim, Lighting, AC duct work, Handicap Ramps and hand rails, Bathroom sink lowering, installation of grab bars, and stall reconfiguration for ADA compliance. |
14-002 |
GMU |
$14,790.00 |
$4,930.00 |
$0.00 |
$0.00 |
$19,720.00 |
Application of seal coat to terminal and hangar parking areas. |