13-009 LKR $8,183.00 $8,183.00 $310,956.00 $0.00 $327,322.00 2011 Taxilane Rehabilitation Project.
13-008 3J1 $43,620.45 $29,080.30 $0.00 $0.00 $72,700.75 Property Option Acquisitions Scope includes: 1. Conduct a title search for all properties proposed for fee simple acquisition only, and fee simple acquisition and avigation easement combined (total of 8). 2. Prepare appraisals for all 28 properties. 3. Prepare review appraisals for the 8 properties addressed in 1 above. 4. Prepare options for and negotiate with the 8 property owners addressed in 1 above.
13-007 HVS $10,129.00 $3,376.00 $0.00 $0.00 $13,505.00 Rotating beacon replacement, and painting of beacon tower.
13-006 GGE $7,230.51 $7,230.53 $130,149.36 $0.00 $144,610.40 1. Hangar Taxilane Extension 2. Land Acquisition - Doar Property 3. DBE Plan Update (FY'12-FY'14) and Small Business Participation Plan
13-005 PHH $2,854.75 $2,854.75 $51,385.50 $0.00 $57,095.00 Construct Taxiway to Hangar Area - Design and Bid Only
13-004A 3J1 $7,528.00 $5,018.00 $0.00 $0.00 $12,546.00 Public hearing necessary for the satisfaction of NEPA requirements. This is part of the Environmental Assessment
13-004 3J1 $102,045.00 $68,030.00 $0.00 $0.00 $170,075.00 Airport Layout Plan Update & Environmental Assessment. This request if the first of the planning, design, and construction of the newly re-aligned runway at the current site of the Ridgeland Airport. Re-alignment is necessary to bring the airport into FAA standards, and for the protection of the school across HWY 278.
13-003 ARW $26,250.00 $8,750.00 $0.00 $0.00 $35,000.00 Airport Terminal Building Maintenance - including restroom renovations and skylight repairs.
13-002 CKI $21,833.00 $7,278.00 $0.00 $0.00 $29,111.00 Airport Terminal Building Maintenance - including roof repairs and painting.
13-001 CUB $19,038.00 $19,039.00 $342,690.00 $0.00 $380,767.00 Taxiway 'A' extension, design, and permitting (Phase I). The primary need for the proposed project is to improve airfield safety by eliminating back taxiing on Runway 13-31.
12-027 99N $12,420.00 $12,420.00 $223,560.00 $0.00 $248,400.00 Design/Construction of security fencing and gates.
12-026 GGE $6,561.00 $6,561.00 $118,098.00 $0.00 $131,220.00 Rehabilitate TWY A, including taxiway connectors.
12-025 EOE $4,301.00 $4,301.00 $77,420.00 $0.00 $86,022.00 Apron rehabilitation and expansion (design only).
12-023 GRD $1,596.00 $1,595.50 $60,626.00 $0.00 $63,817.50 Runway 9 Approach Survey and Clearing (FY2011)
12-022 BBP $4,841.00 $13,036.00 $160,893.00 $0.00 $178,770.00 NAVAID Rehabilitation (PAPI, REIL, and Regulator) Land Acquisition Approach Clearing (Design and Bidding Only)
12-021 FDW $6,775.00 $6,775.00 $121,950.00 $0.00 $135,500.00 Engineering Design Services to improve runway safety area
12-020 HVS $10,984.00 $10,983.50 $197,703.00 $0.00 $219,670.50 Runway Safety Area Development (Design) and Approach Obstruction Clearing - RWY 3 and RWY 21 (Design)
12-019 MNI $29,420.00 $29,420.00 $529,560.00 $0.00 $588,400.00 The project consists of surveying obstructions located on properties adjacent to the south end runway, conducting FAA appraisals of the properties that have obstructions that will have to be removed, obtaining navigational easements on those properties and removing the identified obstructions in order to bring the runway up to an LPV of 34:1 per FAA recommendation. Additional navigational easements will be obtained on properties adjacent to the north end runway to allow for additional obstructions to be removed.
12-018 MNI $9,250.00 $9,250.00 $166,500.00 $0.00 $185,000.00 The project consists of surveying obstructions located on properties adjacent to the north runway end, obtaining navigational easements on those properties and removing the identified obstructions in order to accomplish an LPV instrument approach meeting FAA 34:1 criteria.
12-017 HXD $16,061.00 $16,061.00 $289,098.00 $0.00 $321,220.00 Lighted Sign Replacement Runway 21 Tree Removal