11-013 |
HVS |
$5,678.00 |
$9,011.00 |
$279,086.00 |
$0.00 |
$293,775.00 |
Professional service fees to facilitate land and easement acquisition to both approach and departure areas of runway 3 and runway 21. |
11-012 |
LQK |
$4,010.00 |
$20,335.00 |
$136,025.00 |
$0.00 |
$160,370.00 |
Engineering, administration, and legal services for acquiring land along RWY 5/23 including planning services for updating the airport layout plan. |
11-011 |
CQW |
$1,974.00 |
$1,974.00 |
$75,000.00 |
$0.00 |
$78,948.00 |
Engineering design services for completing a full parallel taxiway to RWY 8/26 |
11-010A |
GGE |
$5,118.00 |
$5,118.00 |
$92,129.00 |
$0.00 |
$102,365.00 |
Amendment to 11-010
FAA awarded an additional amount of money for the cost of materials for installation of an emergency backup generator for GGE. |
11-010 |
GGE |
$48,679.00 |
$41,803.00 |
$1,065,859.00 |
$0.00 |
$1,156,341.00 |
Install new LED runway and taxiway edge lights including omni-directional approach lighting equipment on approach end of runway 5. |
11-008 |
CDN |
$12,750.00 |
$12,750.00 |
$484,500.00 |
$0.00 |
$510,000.00 |
Engineering and construction services for relocating and rehabilitating TWY "F" |
11-007 |
JZI |
$133,508.48 |
$44,502.82 |
$502,651.00 |
$0.00 |
$680,662.30 |
Airfield maintenance project - Replace selective excessive cracked concrete slabs on runway 4/22 and associated connecting taxiways, joint seal existing concrete pavement and apply runway and taxiway markings. |
11-006 |
FDW |
$71,135.00 |
$71,135.00 |
$2,703,130.00 |
$0.00 |
$2,845,400.00 |
Rehabilitate the asphalt pavements of Runway 4/22, the parallel taxiway, and apron with a three inch bituminous asphalt overlay including reimbursement for tree obstruction removal on both runway ends. |
11-005 |
BBP |
$8,081.00 |
$2,694.00 |
$0.00 |
$0.00 |
$10,775.00 |
Install new rotating beacon |
11-004 |
CEU |
$61,798.00 |
$41,197.00 |
$0.00 |
$0.00 |
$102,995.00 |
Construct t-hangar apron area and taxilanes. |
11-003 |
CDN |
$45,360.00 |
$30,240.00 |
$0.00 |
$0.00 |
$75,600.00 |
Preliminary and final engineering design services including bidding assistance services for Taxiway "F" |
11-002 |
HXD |
$32,718.00 |
$32,718.00 |
$1,243,296.00 |
$0.00 |
$1,308,732.00 |
RWY 21 Approach: a) airport tree obstruction removal and on airport tree mitigation; b) design service for RWY 3/21 lighted sign relocation; c) legal fees for easement acquisition for off-airport tree obstruction removal; and d) develop a disadvantage business enterprise plan |
11-001 |
GGE |
$8,868.00 |
$11,936.00 |
$395,275.00 |
$0.00 |
$416,079.00 |
Runway 23 safety area grading and continuance of environmental mitigation monitoring. |
10-023 |
FDW |
$12,217.00 |
$12,217.00 |
$464,260.00 |
$0.00 |
$488,694.00 |
Land easement acquisition and obstruction clearing |
10-022 |
6J0 |
$13,535.00 |
$13,535.00 |
$507,201.00 |
$0.00 |
$534,271.00 |
Realign a portion of parallel taxiway "A" |
10-021 |
FLO |
$90,266.00 |
$90,266.00 |
$3,430,097.00 |
$0.00 |
$3,610,629.00 |
Reconstruct and expand commercial service terminal apron |
10-020AA |
SMS |
$59,770.00 |
$39,847.00 |
$0.00 |
$0.00 |
$99,617.00 |
Contract arbitrator determination awarded payment of an additional 70,000 CY dirt embankment for runway safety area improvement including half of the arbitrator administration fee. |
10-020A |
SMS |
$5,237.00 |
$5,237.00 |
$199,006.00 |
$0.00 |
$209,480.00 |
Grant Amendment - Change Order for DHEC stormwater sediment basin, stream mitigation. |
10-020 |
SMS |
$34,915.00 |
$34,916.00 |
$1,326,797.00 |
$0.00 |
$1,396,628.00 |
Construction of runway 5/23 safety area enhancement including wetland & stream mitigation and monitoring. |
10-019 |
PYG |
$2,475.00 |
$825.00 |
$0.00 |
$0.00 |
$3,300.00 |
Replace rotating beacon motor |