05-004 |
CKI |
$3,766.00 |
$3,766.00 |
$67,788.00 |
$0.00 |
$75,320.00 |
Update the airport layout plan and have engineering design services rehabilitate the stub taxiway and apron areas with a five inch concrete overlay |
05-002 |
CEU |
$6,000.00 |
$2,000.00 |
$0.00 |
$0.00 |
$8,000.00 |
Refurbish rotating beacon |
05-001 |
PHH |
$41,432.00 |
$41,432.00 |
$1,574,426.00 |
$0.00 |
$1,657,290.00 |
Rehabilitate runway 18/36, stub taxiway, and apron pavements, improve the runway safety areas, install a new medium intensity runway lighting system and lighting vault, install precision approach path indicators (PAPI), and a new rotating beacon. |
04-028 |
LKR |
$4,192.00 |
$4,192.00 |
$159,296.00 |
$0.00 |
$167,680.00 |
Runway 6 one hundred foot threshold relocation and automated weather observation system (AWOS) design project. |
04-027 |
GRD |
$2,211.00 |
$2,211.00 |
$84,031.00 |
$0.00 |
$88,453.00 |
Design services for rehabilitating taxiway "D". |
04-026 |
GGE |
$550,000.00 |
$1,250,000.00 |
$0.00 |
$0.00 |
$1,800,000.00 |
Construct new terminal building |
04-025 |
CUB |
$259,791.00 |
$2,698,313.00 |
$1,640,761.00 |
$0.00 |
$4,598,865.00 |
Construct a new general aviation terminal building and t-hangar taxiways |
04-024 |
BBP |
$2,488.00 |
$2,488.00 |
$94,550.00 |
$0.00 |
$99,526.00 |
Apron resealing and marking, including the replacement of runway lighting cables. |
04-023 |
HVS |
$2,072.00 |
$2,072.00 |
$78,746.00 |
$0.00 |
$82,890.00 |
Clearing and grubbing of runway 21 approach |
04-022 |
FDW |
$30,208.00 |
$30,208.00 |
$1,147,885.00 |
$0.00 |
$1,208,301.00 |
Preliminary and final engineering design and construction services for a 500' runway and parallel taxiway extension; including obstruction clearing in the approach to runway 23. |
04-021 |
RBW |
$1,070.00 |
$1,070.00 |
$40,660.00 |
$0.00 |
$42,800.00 |
Update the airport layout plan. |
04-020 |
CQW |
$3,502.00 |
$3,503.00 |
$133,095.00 |
$0.00 |
$140,100.00 |
Installation of an automated weather observation system with precipitation and thunderstorm sensors (AWOS III P/T) |
04-019 |
DYB |
$63,750.00 |
$21,250.00 |
$0.00 |
$0.00 |
$85,000.00 |
Rejuvenate runway 6/24, parallel taxiway, and apron including painting of the airfield markings. |
04-018 |
GMU |
$11,758.00 |
$11,758.00 |
$446,794.00 |
$0.00 |
$470,310.00 |
Install security fencing and gates. |
04-017 |
MKS |
$17,750.00 |
$17,750.00 |
$674,500.00 |
$0.00 |
$710,000.00 |
Extend runway 5 (550' x 75'); construct taxiway turnaround; install medium intensity runway edge lights; and obstruction (tree) clearing. |
04-016 |
CKI |
$12,833.00 |
$12,833.00 |
$487,640.00 |
$0.00 |
$513,306.00 |
A concrete overlay of the existing apron and stub taxiway including storm drainage improvements. |
04-015 |
LQK |
$26,600.00 |
$26,600.00 |
$1,010,800.00 |
$0.00 |
$1,064,000.00 |
Rehabilitate the runway and apron asphalt pavement with a asphalt overlay including pavement markings and continuation of the t-hangar taxiway development project. |
04-014 |
SPA |
$2,134.00 |
$2,134.00 |
$81,100.00 |
$0.00 |
$85,368.00 |
Installation of taxiway "B" medium intensity lighting system. |
04-013 |
CEU |
$3,250.00 |
$3,250.00 |
$58,500.00 |
$0.00 |
$65,000.00 |
Conduct a "Preliminary Engineering Study for runway 7/25 extension". The study will identify runway extension options based on unrestricted and restricted lengths, sitting of a future precision NAVAIDS, re-routing highway SC-37, and the surrounding land use considerations. Detail cost estimates will be prepared for each option. |
04-012 |
DCM |
$31,975.00 |
$31,975.00 |
$1,215,057.00 |
$0.00 |
$1,279,007.00 |
Rehabilitate runway 17/35 - project will include pavement reclamation of the existing runway, asphalt pavement removal, and placement of 3" of bituminous surface course |