02-002 LQK $11,040.00 $279,245.00 $0.00 $0.00 $290,285.00 Construct taxiways to serve a new 12 unit t-hangar.
02-001 GGE $26,250.00 $8,750.00 $0.00 $0.00 $35,000.00 Re-mark runway 5/23.
01-036 GRD $54,024.00 $54,024.00 $972,425.00 $0.00 $1,080,473.00 Rehabilitate asphalt pavement and lighting system for taxiway "A" including the two connecting taxiways to runway 9/27.
01-033 LUX $37,500.00 $12,500.00 $0.00 $0.00 $50,000.00 Crack seal airfield pavement
01-032 SMS $38,925.00 $12,975.00 $0.00 $0.00 $51,900.00 Approach and transitional clearing along runway 5/23.
01-031 DYB $16,352.00 $16,353.00 $294,343.00 $0.00 $327,048.00 Perform planning services for an environmental assessment, including a wetland permitting and mitigation plan.
01-030A LUX $7,500.00 $2,500.00 $0.00 $0.00 $10,000.00 Grant amendment for rejuvenate the airfield pavement
01-030 LUX $45,000.00 $15,000.00 $0.00 $0.00 $60,000.00 Rejuvenate airfield pavement
01-029 3J1 $14,491.00 $14,492.00 $260,846.00 $0.00 $289,829.00 Site selection study for a new airport. Professional services will accomplish an environmental assessment, a master plan study, airport layout plans, and a disadvantage business enterprise (DPE) plan.
01-028 OGB $5,670.00 $5,670.00 $0.00 $0.00 $11,340.00 Apply a fuel resistant sealer to the apron.
01-027 OGB $50,000.00 $50,000.00 $900,000.00 $0.00 $1,000,000.00 Remove obstructions (trees) along runway 17/35, install security fencing, and property acquisition.
01-026 CKI $5,366.00 $5,367.00 $96,599.00 $0.00 $107,332.00 Design of runway lighting improvements; install precision approach path indicator lights, rotating beacon, and erect a new beacon tower.
01-025 GMU $42,382.00 $42,382.00 $762,877.00 $0.00 $847,641.00 Relocate and install a new high intensity runway lighting system, rehabilitate medium intensity taxiway lights on taxiways "A" and "B", relocate runway and taxiway signage. Basic engineering design and construction administration services for rehabilitating runway 1/19.
01-023 CDN $8,333.00 $8,334.00 $150,000.00 $0.00 $166,667.00 Install automated weather observation system (AWOS III P-T) with runway surface condition sensors and airfield pavement crack sealing.
01-022 FDW $6,111.00 $6,111.00 $110,000.00 $0.00 $122,222.00 Installation of a automated weather observation system (AWOS III) and ground communication outlet (GCO).
01-021 FLO $91,778.00 $91,778.00 $1,652,000.00 $0.00 $1,835,556.00 Rehabilitate runway 9/27 with an asphalt overlay including precision instrument markings. Install high intensity runway lights (HIRLS) and distance remaining signs on runway 9/27. Install runway end identification lights (REILS) on runway 1,19, and 27. Phase III, improve runway safety area in the approach to runway 9.
01-020 MKS $48,336.00 $48,336.00 $870,048.00 $0.00 $966,720.00 Extend partial parallel taxiway "A" to a full parallel taxiway. Overlay and rehabilitate the existing taxiway "A" and install medium intensity taxiway lights. Update the airport layout plan.
01-019 AIK $8,333.00 $8,334.00 $150,000.00 $0.00 $166,667.00 Environmental assessment and design for a 500' runway extension including surveying and geotechnical services for rehabilitating runway 6/24. Installation of security fencing.
01-018 CQW $8,333.00 $8,334.00 $150,000.00 $0.00 $166,667.00 Basic engineering design services for a 600' runway extension to runway 25, including environmental assessment for constructing a taxiway turnaround.
01-017 AND $8,333.00 $8,333.00 $150,000.00 $0.00 $166,666.00 Phase I, preliminary engineering, project formulation, and environmental assessment for extending runway 5/23 from 5000' to 6000'.