00-004 |
CEU |
$26,347.00 |
$26,347.00 |
$0.00 |
$0.00 |
$52,694.00 |
Construct stone base and asphalt surface coarse, pavement markings, and permanent grassing for hangar taxi lanes including associated engineering and professional cost affiliated with paving of the taxilanes serving 14 hangar units. |
00-003 |
ARW |
$6,250.00 |
$6,250.00 |
$0.00 |
$0.00 |
$12,500.00 |
Update the airport layout plan |
00-002 |
GYH |
$48,843.00 |
$48,842.00 |
$879,165.00 |
$0.00 |
$976,850.00 |
Installation of high intensity runway edge lights (HIRLS) and approach lighting system including rail lights (MALSR). Updating the airport master plan. |
00-001 |
LQK |
$56,000.00 |
$56,000.00 |
$0.00 |
$0.00 |
$112,000.00 |
Installation of an automated weather observation station (AWOS III) and associated equipment, including engineering design. |
99-023 |
CUB |
$18,788.00 |
$18,788.00 |
$338,184.00 |
$0.00 |
$375,760.00 |
Installation of new medium intensity runway and taxiway lighting system, precision approach path indicator lights (PAPI'S), and construct new electrical vault. |
99-022 |
AIK |
$200,000.00 |
$960,000.00 |
$0.00 |
$0.00 |
$1,160,000.00 |
Construct new terminal building addition. |
99-021 |
CEU |
$13,356.50 |
$13,356.50 |
$240,417.00 |
$0.00 |
$267,130.00 |
(1) Preparation of plans and specifications through bidding for runway 7/25 overlay, widening, and extension; apron rehabilitation and overlay; and runway safety area improvements. (2) Cemetery analysis and relocation plan (3) Preliminary engineering for |
99-020 |
CEU |
$20,959.09 |
$20,959.09 |
$377,263.80 |
$0.00 |
$419,182.00 |
Relocate Cemetery in Runway 7 Safety Area |
99-019 |
GYH |
$262,500.00 |
$87,500.00 |
$0.00 |
$0.00 |
$350,000.00 |
Runway 5/23 concrete joint sealing and asphalt rehabilitation. |
99-018 |
LQK |
$61,208.00 |
$77,100.00 |
$1,244,759.00 |
$0.00 |
$1,383,067.00 |
Land surveying and appraisal fees; engineering design and construction of the partial parallel taxiway. |
99-017 |
UDG |
$8,431.00 |
$8,431.00 |
$0.00 |
$0.00 |
$16,862.00 |
Install 3,200' of 6' high and 1,000' of 4' high chain link fence. Install three 24' wide 6' high double gates and one 24' wide 4' high double gate. |
99-016 |
AIK |
$27,000.00 |
$9,000.00 |
$0.00 |
$0.00 |
$36,000.00 |
Rout, clean, sterilize, and crack seal runway 6/24 and connecting taxiways. |
99-015A |
LKR |
$1,945.00 |
$1,945.00 |
$0.00 |
$0.00 |
$3,890.00 |
Amend 99-015 grant for replacing the non-directional beacon by adding a SA25 AC Single Transmitter. |
99-015 |
LKR |
$4,800.00 |
$4,800.00 |
$0.00 |
$0.00 |
$9,600.00 |
Replace Non-directional beacon. |
99-014 |
CUB |
$3,835.00 |
$3,835.00 |
$69,024.00 |
$0.00 |
$76,694.00 |
(Phase I) Engineering design services for rehabilitating the airfield lighting system. |
99-013 |
GMU |
$350,000.00 |
$350,000.00 |
$0.00 |
$0.00 |
$700,000.00 |
Overlay runway 10/28 and rehabilitate portions of the south aircraft parking apron. |
99-012 |
35A |
$25,920.00 |
$25,920.00 |
$0.00 |
$0.00 |
$51,840.00 |
Update the airport layout plan, aerial topographic mapping, survey control points, and a boundary property plat. |
99-011 |
CRE |
$7,100.00 |
$7,100.00 |
$127,800.00 |
$0.00 |
$142,000.00 |
Prepare airport layout plan updates for Grand Strand Airport and Conway-Horry County Airport, including updating the Horry County general aviation system plan. |
99-010A |
SPA |
$3,360.00 |
$1,120.00 |
$0.00 |
$0.00 |
$4,480.00 |
Crack seal associated taxiways to runway 5/23. |
99-010 |
SPA |
$18,750.00 |
$6,250.00 |
$0.00 |
$0.00 |
$25,000.00 |
Crack seal runway 5/23 and the associated connecting taxiways |