01-016 |
MNI |
$88,500.00 |
$29,500.00 |
$0.00 |
$0.00 |
$118,000.00 |
Rejuvenate the airfield's asphalt pavement, including runway and taxiway markings. |
01-015 |
RBW |
$4,716.00 |
$4,716.00 |
$84,889.00 |
$0.00 |
$94,321.00 |
Phase I design services for strengthen and extending runway 5/23. |
01-014 |
OGB |
$54,991.50 |
$54,991.50 |
$0.00 |
$0.00 |
$109,983.00 |
Rehabilitate the existing apron by placing a single surface treatment and a nominal 2" asphalt overlay. |
01-013 |
PHH |
$3,075.00 |
$3,075.00 |
$55,345.00 |
$0.00 |
$61,495.00 |
Design services for rehabilitating the airfield pavement and lighting system. |
01-012 |
LQK |
$8,333.00 |
$8,333.00 |
$150,000.00 |
$0.00 |
$166,666.00 |
Rehabilitate medium intensity runway lights, and install perimeter fencing. |
01-010 |
52J |
$2,850.00 |
$2,850.00 |
$51,300.00 |
$0.00 |
$57,000.00 |
Prepare an airport layout plan |
01-009 |
ARW |
$45,391.46 |
$15,130.48 |
$0.00 |
$0.00 |
$60,521.94 |
Rejuvenate, crack seal, and mark runway 6/24. |
01-008 |
SMS |
$11,900.00 |
$11,900.00 |
$214,200.00 |
$0.00 |
$238,000.00 |
Complete Phase II airfield lighting project, engineering design services for rehabilitating portions of the parallel taxiway and terminal apron, update the airport layout plan, and install a thunderstorm sensor on the AWOS system. |
01-007 |
GGE |
$7,173.50 |
$7,173.50 |
$129,123.00 |
$0.00 |
$143,470.00 |
Design services for rehabilitating parallel taxiway "A" and installing medium intensity taxiway lights, including engineering planning services for updating the height limitation zoning ordinance and the airport layout plan with a narrative report. |
01-006 |
GGE |
$46,181.00 |
$46,181.00 |
$831,257.00 |
$0.00 |
$923,619.00 |
Rehabilitate parallel taxiway "A" and install medium intensity taxiway lights. |
01-005 |
UDG |
$3,456.65 |
$3,456.65 |
$62,219.00 |
$0.00 |
$69,132.30 |
Design services for rehabilitating and expanding the terminal area aircraft parking apron. |
01-004 |
CEU |
$105,172.66 |
$105,172.65 |
$1,893,108.00 |
$0.00 |
$2,103,453.31 |
Re-construct runway 7-25 by widening, extending, and placing an asphalt overlay; rehabilitating the apron; and improving the runway safety areas. |
01-003 |
OGB |
$3,135.00 |
$3,135.00 |
$0.00 |
$0.00 |
$6,270.00 |
Install a ground-link system to provide direct voice communication to the FAA air traffic control center. |
01-002 |
OGB |
$54,737.00 |
$54,737.00 |
$985,266.00 |
$0.00 |
$1,094,740.00 |
Pave parallel taxiway to runway 17/35 and portions of taxiway "A", parallel to runway 5/23. Install medium intensity taxiway edge lights and identification signs on the parallel taxiway to runway 17/35. Update the airport master plan. |
01-001 |
UZA |
$26,106.00 |
$26,106.00 |
$150,000.00 |
$0.00 |
$202,212.00 |
Rehabilitate taxiway "J' pavement and edge lights, including storm drainage improvements. |
00-022 |
AND |
$12,450.00 |
$12,450.00 |
$224,100.00 |
$0.00 |
$249,000.00 |
Rehabilitate taxiway lighting system. |
00-021 |
AND |
$12,000.00 |
$4,000.00 |
$0.00 |
$0.00 |
$16,000.00 |
Crack seal asphalt pavements of runway 5/23 and the connecting taxiways. |
00-019 |
35A |
$500,000.00 |
$0.00 |
$0.00 |
$0.00 |
$500,000.00 |
Construct two 10-unit t-hangars and connecting taxilanes. |
00-018A |
GMU |
$1,689.00 |
$1,689.00 |
$30,402.00 |
$0.00 |
$33,780.00 |
Grant amendment to cover cost overruns for the installation of MALSF on runway 1 and REILS on runway 19. |
00-018 |
GMU |
$27,425.00 |
$27,426.00 |
$493,655.00 |
$0.00 |
$548,506.00 |
Install a medium intensity approach lighting system with flashers (MALSF) on runway 1 and runway end identifier lights (REILS) on runway 19. |